Project Timeline

Milestone

Approval / Comment

Expected Completion

Determine need to replace Fire Station 2

Council ratified Motion 09-GC-026

February 4, 2008

Review of Current Fire Station 2 Functionality

Council ratified Motion 21-GC-248 approving the Fire Master Plan

October 12, 2021

Decision on whether to move station or rebuild in same place

Council ratified Motion 22-GC-079/080

June 8, 2022

Complete initial location analysis

Council ratified Motion 22-GC-079/080

June 8, 2022

Complete additional location analysis and search out available suitable land

Fire Department 2024 Business Plan Item
FD-01 and findings reported in Staff Report FD003-24

February 14, 2024 (Budget and Business Plan approval)

May 7, 2024 (Staff Report FD003-24)

Acquisition / selection of new site

Authorization included in motion of Staff Report FD003-24

May 7, 2024 / May 15, 2024

Present Concept Site Layout and Concept Design of Station

Included for reference in Staff Report
FD003-24

May 7, 2024 / May 15, 2024

Public Consultation to gain feedback on functions and amenities

Authorization to move forward included in motion of Staff Report FD003-24

Summer / Fall 2024

Request for Proposals (RFP) for Design / Build

Authorization to move forward included in motion of Staff Report FD003-24

Pre-qualification – Summer / Fall 2024

RFP – Winter 2025

Award of Design-Build Contract

Staff Report to General Committee to award contract and update costing

Winter / Spring 2025

Site Works

Entrance, initial site work

2025

Substantial Construction

Construction of facility

2026

Occupancy

2026

Grand Opening

To coincide with Fire Department 150 Celebrations

2026